Pookottur
Grama Panchayath
SO : SEUF
Pookottur Grama
Panchayath consists of plain land, valley hills and laterite hillocks.
The hill areas are mainly quarries. This historically important
Grama Panchayath faces acute shortage of water during the period
from January to May and till the monsoon starts. Kudumbasree was
the supporting organization for the pre-planning and planning phase
and SEUF is the supporting organization
for the implementation phase.
The organisational
setup of Kudumbasree
|
1
|
Team Leader
|
- |
1
|
|
2
|
Project
Engineers
|
- |
2
|
|
3
|
Community
Organisers
|
- |
2
|
|
4
|
Community
facilitators
|
- |
19
|
|
5
|
CBNP Volunteers
|
- |
3
|
The CBNP is
the motivating force in this Grama Panchayath along with the other
government machineries and local bodies. There was enthusiastic
participation of women in neighbourhood groups! After conducting
socio-economic survey and study at field level, 22 areas, where
the drinking water scarcity is faced, were identified. Getting safe
drinking water is the first priority and environmental sanitation
and women development initiatives are the other prioritized activities.
21 water supply schemes have been approved by BGs in all respects
and CEPs prepared by SOs with the involvement of BGs. The total
project cost for the Water supply schemes is Rs. 2,13,12,600/-.
The GP has already provided Rs. 16 lakhs from their plan allocation
to meet 10% contribution. IPQA, have been signed for all the 21
projects.
| 1. |
Population |
: |
25253 |
| |
|
Male |
: |
12603 |
| |
|
Female |
: |
12650 |
| |
|
Scheduled
Caste |
: |
1793 |
| |
|
Literacy |
: |
78
% |
| |
|
No.
of Households |
: |
4209 |
| |
|
(a)
House holds covered by |
: |
|
| |
|
|
KRWSA
Scheme |
: |
1546
(37%) |
| |
|
|
Population |
: |
12793. |
| 2. |
Total
Wards |
: |
14 |
| 3. |
Total
outlay of project at GP level (Proposal) |
: |
Rs.
2,51,46,802 |
| |
|
BG
Share |
: |
Rs.
46,38,455 |
| |
|
GP
Share |
: |
Rs.
22,17,670 |
| |
|
GOK
Share |
: |
Rs.
1,82,90,678 |
| 4. |
Total
Projects |
: |
21
- All OD Wells source |
| 5. |
Project
Cost (WSS) |
: |
Rs.
2,13,12,600 |
| |
|
GOK |
: |
Rs.
1,59,84,450 |
| |
|
GP |
: |
Rs.
21,31,260 |
| |
|
BG |
: |
Rs.
31,96,890 |
| 6. |
Cost
per family |
: |
Rs.
13,786 |
| |
O
& M Cost |
: |
Rs.
35/- per month/HH |
| 7. |
KWA
Schemes proposed to be taken over |
: |
2 |
| |
Public
taps |
: |
118
Nos. |
| |
House
connections |
: |
77
Nos. |
| 8. |
Latrines
- New |
: |
211
Nos. |
| |
|
Cost |
: |
Rs.
8,44,000/- |
| |
|
BG
Contribution |
: |
Rs.
4,22,000/- |
| |
Conversion
of Latrines |
: |
14
Nos |
| |
|
Cost |
: |
Rs.
21,000/- |
| |
|
BG
Contribution |
: |
Rs.
14,000/- |
|