Pookottur Grama Panchayath
SO :

Pookottur Grama Panchayath consists of plain land, valley hills and laterite hillocks. The hill areas are mainly quarries. This historically important Grama Panchayath faces acute shortage of water during the period from January to May and till the monsoon starts. Kudumbasree was the supporting organization for the pre-planning and planning phase and is the supporting organization for the implementation phase.

The organisational setup of Kudumbasree

1

Team Leader

-

1

2

Project Engineers

-

2

3

Community Organisers

-

2

4

Community facilitators

-

19

5

CBNP Volunteers

-

3

The CBNP is the motivating force in this Grama Panchayath along with the other government machineries and local bodies. There was enthusiastic participation of women in neighbourhood groups! After conducting socio-economic survey and study at field level, 22 areas, where the drinking water scarcity is faced, were identified. Getting safe drinking water is the first priority and environmental sanitation and women development initiatives are the other prioritized activities. 21 water supply schemes have been approved by BGs in all respects and CEPs prepared by SOs with the involvement of BGs. The total project cost for the Water supply schemes is Rs. 2,13,12,600/-. The GP has already provided Rs. 16 lakhs from their plan allocation to meet 10% contribution. IPQA, have been signed for all the 21 projects.

1. Population : 25253
    Male : 12603
    Female : 12650
    Scheduled Caste : 1793
    Literacy : 78 %
    No. of Households : 4209
    (a) House holds covered by :  
      KRWSA Scheme : 1546 (37%)
      Population : 12793.
2. Total Wards : 14
3. Total outlay of project at GP level (Proposal) : Rs. 2,51,46,802
    BG Share : Rs. 46,38,455
    GP Share : Rs. 22,17,670
    GOK Share : Rs. 1,82,90,678
4. Total Projects : 21 - All OD Wells source
5. Project Cost (WSS) : Rs. 2,13,12,600
    GOK : Rs. 1,59,84,450
    GP : Rs. 21,31,260
    BG : Rs. 31,96,890
6. Cost per family : Rs. 13,786
  O & M Cost : Rs. 35/- per month/HH
7. KWA Schemes proposed to be taken over : 2
  Public taps : 118 Nos.
  House connections : 77 Nos.
8. Latrines - New : 211 Nos.
    Cost : Rs. 8,44,000/-
    BG Contribution : Rs. 4,22,000/-
  Conversion of Latrines : 14 Nos
    Cost : Rs. 21,000/-
    BG Contribution : Rs. 14,000/-